B
Bob
Ok.
I'm not sure if this is a simple matter for you folks or not.
I am a Manager of an IT Department. My boss has this thing he calls 'TND'
short for Task/Name/Date
what it is is a list of work tasks by name with a particular date of
completion.
This list is kind of an executive summary of tasks / projects he's doled out
to the IT department.
What I want to do is somehow convert that list into a project plan document
and create an executive summary / gantt chart so he can track progress.
It's the typicall IT stuff: Too much work, not enough resources. I need to
show him that i can manage this by balancing the resources we have over time
and assignment by project.
1. can project help me with this?
2. How do i go about creating this structure? A master project with sub
projects?
3. how do i list 'queued' work, e.g., work that is not planned yet but is
more of in the 'work queue' that has a lower priority.
4. how can i give him a simple summary report showing progress, allocated
resources to projects, and the work queue as an executive summary report.
basically, I need to present him weekly with a list of Projects
(active/queued), Priority, Schedule, Resource Allocation in some very
simple, graphical means.
Some of our projects are like this:
1. Develop Crystal Reports Web Intranet
a. 100 Man Hours, (1) Resource (crystal developer)
b. Status: In Progress, 25% complete
c. Start Date, Dec 1, 2004, est Completion Date 6/1/2005
2. Rebuild Citrix Farm
a. 400 Man Hours (2) Resources (Network Admins)
b. Status: In Progress (5%) complete
c. Start Date, Jan 1, 2005, est Completion Date 9/2005
3. Implement Security Best Practices in A/D
a. 80 Man Hours (2) Resources (Network Admins)
b. Status, Not Started (0%) Complete
c. Start Date: 9/1/2005 end date, 12/31/2005
etc.
Pretty typical IT Stuff.
Basically, he wants to see a summary report Gantt Chart Listing Active and
Pending WORK, schedule, Resource Allocation.
We have too much work, not enough resources, and I need to SHOW it to him.
He's being totally REASONABLE in his request.
What i'm wondering is if I keep one project Plan for each Project (task in
his book), and a common set of shared resources across all projects, will I
be able to make a summary project that includes all pending and current
work, show resource allocation, and summary Gantt?
is there an executive report add-in that does this?
HELP!
;-)
I can't be the ONLY IT guy that's ever had to do this!
I'm tired of using an excel spreadsheet to manage this and manually
developing a weekly report against project progress,
I'm not sure if this is a simple matter for you folks or not.
I am a Manager of an IT Department. My boss has this thing he calls 'TND'
short for Task/Name/Date
what it is is a list of work tasks by name with a particular date of
completion.
This list is kind of an executive summary of tasks / projects he's doled out
to the IT department.
What I want to do is somehow convert that list into a project plan document
and create an executive summary / gantt chart so he can track progress.
It's the typicall IT stuff: Too much work, not enough resources. I need to
show him that i can manage this by balancing the resources we have over time
and assignment by project.
1. can project help me with this?
2. How do i go about creating this structure? A master project with sub
projects?
3. how do i list 'queued' work, e.g., work that is not planned yet but is
more of in the 'work queue' that has a lower priority.
4. how can i give him a simple summary report showing progress, allocated
resources to projects, and the work queue as an executive summary report.
basically, I need to present him weekly with a list of Projects
(active/queued), Priority, Schedule, Resource Allocation in some very
simple, graphical means.
Some of our projects are like this:
1. Develop Crystal Reports Web Intranet
a. 100 Man Hours, (1) Resource (crystal developer)
b. Status: In Progress, 25% complete
c. Start Date, Dec 1, 2004, est Completion Date 6/1/2005
2. Rebuild Citrix Farm
a. 400 Man Hours (2) Resources (Network Admins)
b. Status: In Progress (5%) complete
c. Start Date, Jan 1, 2005, est Completion Date 9/2005
3. Implement Security Best Practices in A/D
a. 80 Man Hours (2) Resources (Network Admins)
b. Status, Not Started (0%) Complete
c. Start Date: 9/1/2005 end date, 12/31/2005
etc.
Pretty typical IT Stuff.
Basically, he wants to see a summary report Gantt Chart Listing Active and
Pending WORK, schedule, Resource Allocation.
We have too much work, not enough resources, and I need to SHOW it to him.
He's being totally REASONABLE in his request.
What i'm wondering is if I keep one project Plan for each Project (task in
his book), and a common set of shared resources across all projects, will I
be able to make a summary project that includes all pending and current
work, show resource allocation, and summary Gantt?
is there an executive report add-in that does this?
HELP!
;-)
I can't be the ONLY IT guy that's ever had to do this!
I'm tired of using an excel spreadsheet to manage this and manually
developing a weekly report against project progress,