HI,
Have both projects open then select Tools, Organizer.
Select the Calendar tab and make sure your projects are selected in the drop
down lists of open projects at the bottom then select the calendar and click
Copy.
Note: If you copy a calendar, View etc into the Global.Mpt file then the
object becomes available for all projects.
--
Rod Gill
Microsoft MVP for Project
Author of the only book on Project VBA, see:
http://www.projectvbabook.com