file sent to you

J

johnny nui

HI Jan

I have sent you the file.
there must be some simple answer, I just cannot find it.
the file i sent shows the feature working the way I want , and then a few
lines down I cannot get it to work again.
I'm stuck.
thanks
 
J

Jan De Messemaeker

Hi,

The project is Schedule from finish date which reverses some of the logic.
Set it to Schedule from Start and your problem goes away
HTH
 