J
Jon
Dear all
i have a Ms Project Plan set for a go live i ran a couple of weeks back. The
tasks and activities will remain identical for a future go live i have in a
few weeks. The timings (duration and start time) will also remain the same.
However the Start Dates will change by a few weeks so Fri 4th Aug 20:00 will
become Fri 25th Aug 20:00. I have to do this type of change in multiple tasks
in the project, is there an easy way to do a find and replace to ammend all
these dates? There are very few dependencies set on the plan.
Thanks In advance
Jon
i have a Ms Project Plan set for a go live i ran a couple of weeks back. The
tasks and activities will remain identical for a future go live i have in a
few weeks. The timings (duration and start time) will also remain the same.
However the Start Dates will change by a few weeks so Fri 4th Aug 20:00 will
become Fri 25th Aug 20:00. I have to do this type of change in multiple tasks
in the project, is there an easy way to do a find and replace to ammend all
these dates? There are very few dependencies set on the plan.
Thanks In advance
Jon