Finding Overallocation

N

NewsGroup

In a single project the Resource graph helps us find overallocatio.
But if I want to find out if a persons work clashes in 2 or more projects
how should I do?
I inserted the projects into another project and viewed the resource graph,
but there are seperate resource graphs for seperate projects.
How do I bring in 1 resource graph for 2 or more projects?
Please guide me.

Meena.
 
R

Rod Gill

You need to create a resource pool. Search help for Resource Pools. If you
do create a pool, be VERY careful not to rename projects, move them or even
delete any project without first removing them from the pool. Otherwise file
corruption can result.
 