N
netsotov
Hi all,
this is propably some minor problem, but it seems i'm just not able to
figure it out:
when creating tasks and defining relations between them, the tasks keep
'their place' at the project startdate, thereby violating the dependency
which I had just created.
The tasks are fixed unit and or fixed work and i didn't specify further
constraints such as start dates etc and there are no resources assigned.
Thanks,
netsotov
this is propably some minor problem, but it seems i'm just not able to
figure it out:
when creating tasks and defining relations between them, the tasks keep
'their place' at the project startdate, thereby violating the dependency
which I had just created.
The tasks are fixed unit and or fixed work and i didn't specify further
constraints such as start dates etc and there are no resources assigned.
Thanks,
netsotov