I'm very new to MS Project - using Project 2007.
Once I set a baseline for a project, and then go and update the tasks every
couple of days based on progress or delay information received by the team -
how can I have MS Project show that a task was a)finished before the baseline
date AND b) is delayed or finishing after the baseline date?
Thanks in advance