finishing earlier than baseline schedule

P

PaulR

I'm very new to MS Project - using Project 2007.

Once I set a baseline for a project, and then go and update the tasks every
couple of days based on progress or delay information received by the team -
how can I have MS Project show that a task was a)finished before the baseline
date AND b) is delayed or finishing after the baseline date?

Thanks in advance
 
D

Dale Howard [MVP]

PaulR --

Apply the Tracking Gantt view, which allows you to compare the current
schedule (blue and red Gantt bars) against the original Baseline schedule
(gray Gantt bars). Click View - Table - Tracking. You can use this Table
to enter progress in your plan. Enter the date work began on a task in the
Actual Start field, enter the estimated amount of progress in the % Complete
field, and then enter the finish date of the Actual Finish field. Hope this
helps.
 
P

PaulR

Thanks Dale, that's great!

Dale Howard said:
PaulR --

Apply the Tracking Gantt view, which allows you to compare the current
schedule (blue and red Gantt bars) against the original Baseline schedule
(gray Gantt bars). Click View - Table - Tracking. You can use this Table
to enter progress in your plan. Enter the date work began on a task in the
Actual Start field, enter the estimated amount of progress in the % Complete
field, and then enter the finish date of the Actual Finish field. Hope this
helps.
 