roberto1972
Hello !
I would like to request some advice regarding a problem I have : doe
somebody of you know how to assign a fix cost in two different days fo
a same work?
For instance, I have to buy an equipment for $50000 and there is a dow
payment of 30% the day first ($15000)and the rest 70% ($35000) the da
10th.
How do you put this two fix numbers into this work, in its proper
days?
I have been like a whole day trying to find out a solution to this bu
I could not!
Thanks in advance!
Rob