P
pratta
Hi All
I am using Fixed Duration as the default type for planning.
When amending the schedule Project is forcing change of duration saying
"resource is assigned outside of original dates for task#. The duration of
this fixed duration task will change to accomodate the resource assignment".
I then get the resource assignment listed at the wrong % location, and it
steadfastly refuses to accept the required resource unit. Even after I remove
the resource allocation and then add it back!!
This has only happened after installing MS Prof 2003 SP1.
Why don't I get the option to keep the required duration. And why then does
the resource have the wrong work allocated?
The task then lists:
Duration = 1 day. Work=0.5day. Resource1 - 100% - which is clearly incorrect.
Why has Project suddenly decided that a Fixed Duration task is no longer a
Fixed Duration task? Or am I doing something wrong here.
Regards..........Pratta
I am using Fixed Duration as the default type for planning.
When amending the schedule Project is forcing change of duration saying
"resource is assigned outside of original dates for task#. The duration of
this fixed duration task will change to accomodate the resource assignment".
I then get the resource assignment listed at the wrong % location, and it
steadfastly refuses to accept the required resource unit. Even after I remove
the resource allocation and then add it back!!
This has only happened after installing MS Prof 2003 SP1.
Why don't I get the option to keep the required duration. And why then does
the resource have the wrong work allocated?
The task then lists:
Duration = 1 day. Work=0.5day. Resource1 - 100% - which is clearly incorrect.
Why has Project suddenly decided that a Fixed Duration task is no longer a
Fixed Duration task? Or am I doing something wrong here.
Regards..........Pratta