Anders
Hi
Im wondering how to set the time i plan to use to a fixed value even if the
duration is over several days.
Example: Task A, duration 5 hours, start 2006-08-03, finish 2006-08-10
When i try to do this project either changes my finish time to 2006-08-03 or
the duration to 48 hours.
How do i tell Project to leave my values alone??
ps. Sorry if this has been answered before, i did a very quick search but
didn't find anything i thought was the same.
Im wondering how to set the time i plan to use to a fixed value even if the
duration is over several days.
Example: Task A, duration 5 hours, start 2006-08-03, finish 2006-08-10
When i try to do this project either changes my finish time to 2006-08-03 or
the duration to 48 hours.
How do i tell Project to leave my values alone??
ps. Sorry if this has been answered before, i did a very quick search but
didn't find anything i thought was the same.