M
Mike
Does anyone know of a way to "Fix" the date on a milestone
with external dependencies? For example, I have a date of
01/30/04 on my predecessor milestone but the date for my
cross-project successor milestone changed to 01/15/04.
The tool seems to be accepting this change to the
successor and pulling my predecessor date back to 01/15/04
to alleviate the dependency violation. Is there any way
to have the ability to allow the successor to change
without affecting the date on the predecessor? Basically,
I'd like to see the violation in a view/report of some
sort before allowing the predecessor milestone to move
in/out. If anyone out there can help me figure out how to
make a date "stick" no matter what the tool thinks should
happen, please let me know. Thanks
Mike
with external dependencies? For example, I have a date of
01/30/04 on my predecessor milestone but the date for my
cross-project successor milestone changed to 01/15/04.
The tool seems to be accepting this change to the
successor and pulling my predecessor date back to 01/15/04
to alleviate the dependency violation. Is there any way
to have the ability to allow the successor to change
without affecting the date on the predecessor? Basically,
I'd like to see the violation in a view/report of some
sort before allowing the predecessor milestone to move
in/out. If anyone out there can help me figure out how to
make a date "stick" no matter what the tool thinks should
happen, please let me know. Thanks
Mike