B
Bill Easterbrook
I have a Project Engineer who would like to do the following and its been a
while for me:
Assume:
Task A Duration 15 days
Task B
Task C Duration 5 days
They want Task B to be SS+5days to Task A and FF to Task C.
Essentially they want to capture Task B in the plan (which is a series of
Design Reviews that will happen frequently and for small durations over a
period of time) and Start this series of reviews 5 days after Prototyping
Evaluations begin, and end it when Test Reports are written, but they do not
want to create multiple entries at each "review" point. The way it comes
out is Task B ends up with 1 day duration and lots of slack, while the
Project Lead actually wants the duration to be flexible and reflect the
entire duration between Task A and C with slight lag, and change as A and C
do.
any suggestions?
while for me:
Assume:
Task A Duration 15 days
Task B
Task C Duration 5 days
They want Task B to be SS+5days to Task A and FF to Task C.
Essentially they want to capture Task B in the plan (which is a series of
Design Reviews that will happen frequently and for small durations over a
period of time) and Start this series of reviews 5 days after Prototyping
Evaluations begin, and end it when Test Reports are written, but they do not
want to create multiple entries at each "review" point. The way it comes
out is Task B ends up with 1 day duration and lots of slack, while the
Project Lead actually wants the duration to be flexible and reflect the
entire duration between Task A and C with slight lag, and change as A and C
do.
any suggestions?