P
Pinocchio
I would like to create a weekly two-hour recurring task (team meeting), for
the whole duration of a project.
How can I define it if I know neither the number of weeks nor the finish
date of the project (the only option available)?
What is the best practice in this case?
Your MVB (Most Valuable Beginner)
Running Project 2002
the whole duration of a project.
How can I define it if I know neither the number of weeks nor the finish
date of the project (the only option available)?
What is the best practice in this case?
Your MVB (Most Valuable Beginner)
Running Project 2002