B
Boyd
Hi ,
I have a recurring task followed by many small tasks, all assigned to the
same resource. But Project GANTT chart show both recurring and the assigned
tasks running concurrently instead of breaking up the assigned tasks. SHould
it not realize the resource is "busy" during the recurring task?
What is best way to do this?
Normally one would set up a "4 hour" meeting to occur, we'll say, every
Friday morning, then as new new tasks are added, the duration would realize
Friday morning is not available.
I have a recurring task followed by many small tasks, all assigned to the
same resource. But Project GANTT chart show both recurring and the assigned
tasks running concurrently instead of breaking up the assigned tasks. SHould
it not realize the resource is "busy" during the recurring task?
What is best way to do this?
Normally one would set up a "4 hour" meeting to occur, we'll say, every
Friday morning, then as new new tasks are added, the duration would realize
Friday morning is not available.