A
Andrew Skouloudis
Hello everybody.
I have a question about assigning resources on tasks.
Let's say I want to assign a resource on a specific task, that will
work on a specific , strictly defined time frame. For example I want to
add a resource on Task1 that will work for 3 consequent days full time
*but* only for these days. How can I manage to do that?
The only possible solutions I have found so far are the following two :
1. to modify the calendar of this resource to work only in these days
but this wont do the trick since there is a possibilty for this
resource to work to other tasks the rest of the remaining days that I
have set as nonworking days.
2. To set the availabilty of the resource (using the Resource
Availability in the Resource Properties box) for this specific time
frame but this wont do the trick either since the resource will work on
other days as overallocated resource. I can however modify manually the
rest of the days but this is a bit cumbersome.
Thank you in advance (sorry for my english).
I have a question about assigning resources on tasks.
Let's say I want to assign a resource on a specific task, that will
work on a specific , strictly defined time frame. For example I want to
add a resource on Task1 that will work for 3 consequent days full time
*but* only for these days. How can I manage to do that?
The only possible solutions I have found so far are the following two :
1. to modify the calendar of this resource to work only in these days
but this wont do the trick since there is a possibilty for this
resource to work to other tasks the rest of the remaining days that I
have set as nonworking days.
2. To set the availabilty of the resource (using the Resource
Availability in the Resource Properties box) for this specific time
frame but this wont do the trick either since the resource will work on
other days as overallocated resource. I can however modify manually the
rest of the days but this is a bit cumbersome.
Thank you in advance (sorry for my english).