Project 2003: I need to format several bars with a color in the Gantt Chart
based on the customer (eg all "Client" resource tasks I want maroon). Is
there a quick way to format several bars based on a resource at one time?

Thanks in advance.
 
G

Gerard Ducouret

Hello Kay,
In the tool bar, in the filter drop down list, activate the filter "Using
resource...."
then select all the tasks and format them :
Format / Bar

NB : There is another way to do that "dynamically" if the resource move from
a task to another, but it's a little bit more complicated.

Hope this helps,

Gérard Ducouret [Project MVP]
 