Formatting a gantt chart

B

Brad

When trying to print a gantt chart, my project has a begin date of 3/15/05,
yet when I print preview the gantt chart the first column starting from the
left is January 20. These leaves alot of unused space and reduces the view of
the rest of the gantt chart.
 
R

Rod Gill

Try File, Print. You can enter a date range there. Also make sure that under
Project, Project Information the project start date is the same as the
earliest task in your schedule.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top