Formula Next Month

S

Sim

Hi,

Im trying to make a formula in MS Project 2003 that gives me next month
remaining work for a project.

Tx for your help
 
J

Jim Aksel

I think you will need to resort to some VBA for that. If you have a task
with remaining work in the next 4 months I don't think you can nibble just
next month.

Might you try the Task Usage View and change the time scale to monthes? Your
answer would be visible and could be filtered as well.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
B

Brian Kennemer

Jim is correct. you would need VBA to do this if you want a field in a task
view to show the remaining work for the following calendar month for that
task. It is not possible in a formula.
 