M
Marc
I am trying to write a formula in a customized field that will show me which
tasks are:
1.) Overdue
2.) Due in 3 month
3.) Due in 3-6 month
4.) Due in over 6 months
I believe I have one that works, however, it is using the calendar within
project and when it goes out 'X' number of days, it is NOT counting weekends
and holidays.
Below is the formula I have. I believe I need to change the "Project
Calendar" to something else, but I don't know what that "something else" is.
IIf(Text1([Current Date],[Finish],[Project
Calendar])/10560<0,"Overdue",IIf(Text1([Current Date],[Finish],[Project
Calendar])/10560>=0 And Text1([Current Date],[Finish],[Project
Calendar])/10560<3,"Due within 3 months",IIf(Text1([Current
Date],[Finish],[Project Calendar])/10560>=3 And Text1([Current
Date],[Finish],[Project Calendar])/10560<6,"Due between 3 - 6
months",IIf(Text1([Current Date],[Finish],[Project Calendar])/10560>=6,"Due
beyond 6 months",""))))
Can someone please help me?
Thanks!
Marc
tasks are:
1.) Overdue
2.) Due in 3 month
3.) Due in 3-6 month
4.) Due in over 6 months
I believe I have one that works, however, it is using the calendar within
project and when it goes out 'X' number of days, it is NOT counting weekends
and holidays.
Below is the formula I have. I believe I need to change the "Project
Calendar" to something else, but I don't know what that "something else" is.
IIf(Text1([Current Date],[Finish],[Project
Calendar])/10560<0,"Overdue",IIf(Text1([Current Date],[Finish],[Project
Calendar])/10560>=0 And Text1([Current Date],[Finish],[Project
Calendar])/10560<3,"Due within 3 months",IIf(Text1([Current
Date],[Finish],[Project Calendar])/10560>=3 And Text1([Current
Date],[Finish],[Project Calendar])/10560<6,"Due between 3 - 6
months",IIf(Text1([Current Date],[Finish],[Project Calendar])/10560>=6,"Due
beyond 6 months",""))))
Can someone please help me?
Thanks!
Marc