T
Terry Montgomery
Greetings,
I am studying for my PMP exam. I recently took an Estimating & Scheduling
class at a local university. In the class the formula for a Forward Pass was
stated as Early Finish = (Early Start + Task Duration) -1
All the other books and references I am finding on Forward Pass use the same
formula without the -1. The explanation I got from the instructor was that
the class example used Eartly Start = 1 on the first task to begin the
calculation. The other examples I have found set the Eartly Start = 0 on the
first task.
So what's the correct forumla for the test?
Thanks,
I am studying for my PMP exam. I recently took an Estimating & Scheduling
class at a local university. In the class the formula for a Forward Pass was
stated as Early Finish = (Early Start + Task Duration) -1
All the other books and references I am finding on Forward Pass use the same
formula without the -1. The explanation I got from the instructor was that
the class example used Eartly Start = 1 on the first task to begin the
calculation. The other examples I have found set the Eartly Start = 0 on the
first task.
So what's the correct forumla for the test?
Thanks,