From Working Days to Calendar Days

W

Whitney

I have a schedule based on working days, but one line item needs a -14
calendar day lag. I cannot figure out how to make one line item in this
calendar calculate based on calendar days instead of working days. Help!
 
J

JulieS

Hello Whitney,

Set the lag as -14 ed for 14 elapsed days. (Note: An elapsed day to
Project is a 24 hour period of time).

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
J

Jim Aksel

Durations can be entered as "Elapsed Days" so if today is Wednesday and I
enter 5d the task will end next Tuesday. If I enter 5ed the task ends Sunday.
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 