gantt chart filtered for 1 user?

S

sender

is there a way to filter the gantt chart to see just 1 user on the project?

thanks in advance
 
D

Dale Howard

Sender --

Click the Filter drop-down list on the Formatting toolbar, then select the
Using Resource... filter. Choose the desired user from the drop-down list
and click OK. This will filter the display of the Gantt Chart to show only
those tasks to which the resource is assigned. Hope this helps.
 
G

greg

thanks, works good


Dale Howard said:
Sender --

Click the Filter drop-down list on the Formatting toolbar, then select the
Using Resource... filter. Choose the desired user from the drop-down list
and click OK. This will filter the display of the Gantt Chart to show only
those tasks to which the resource is assigned. Hope this helps.
 