Is there a way I can dispaly non-working days on Gantt chart without breaking
down bottom tier to single days
 
J

John

baz said:
Is there a way I can dispaly non-working days on Gantt chart without breaking
down bottom tier to single days

baz,
Sorry, to actually see the non-working days on the Gantt a minor
timescale showing "days" must be displayed.

Your question is interesting because most people want to eliminate the
non-working days so they can see more of the Gantt's full span.

John
Project MVP
 