Gantt notes

G

GOLFNCO

I am using Project 2003 and Excel 2000. When I export my notes from Project
to Excel it cuts some off. Why? How can I transfer the entire notes field
to Excel?
 
J

JulieS

Hi Golfnco,

The export will only capture the first 255 characters stored.

If you do a google search (http://groups.google.com) search for "Notes
export to Excel" in the group microsoft.public.project you'll find
several work arounds.

I hope this helps. Let us know how you get along.

Julie
 
J

John

GOLFNCO said:
I am using Project 2003 and Excel 2000. When I export my notes from Project
to Excel it cuts some off. Why? How can I transfer the entire notes field
to Excel?

Golfnco,
As julie noted, Project truncates at 255 characters, but I have a couple
VBA macros that do it without the truncation. If you are interested, let
me know.

John
Project MVP
jensenj6atatcomcastdotdotnet
(remove obvious redundancies)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top