Stefan Robert
When using the Analyse Timescaled data in Excel... wizard I would like
to be able to get the data exported for the BCWS for up to the end of
the project and get the data ACWP and BCWP only up to the actual date.
When I use the wizard, I can only export up until the Actual Date or
status date for the BCWS, ACWP and BCWP all together. So to get my BCWS
curve up to the end of the project, I put my status date at the end of
the project, but this gives me the ACWP and BCWP curves up to the end
of the project also qhen I would like them to track the Actual date
instead.
I know I could modify the data in Excel manually to get what I want,
but I was wondering if this can be done automatically...
Thanks
Stefan
to be able to get the data exported for the BCWS for up to the end of
the project and get the data ACWP and BCWP only up to the actual date.
When I use the wizard, I can only export up until the Actual Date or
status date for the BCWS, ACWP and BCWP all together. So to get my BCWS
curve up to the end of the project, I put my status date at the end of
the project, but this gives me the ACWP and BCWP curves up to the end
of the project also qhen I would like them to track the Actual date
instead.
I know I could modify the data in Excel manually to get what I want,
but I was wondering if this can be done automatically...
Thanks
Stefan