I have this situation for a task on MS Project Professional 2003 SP2:
Baseline start: 01/26/2007
Baseline finish: 03/14/2007
Baseline cost/work (resource cost=1): 162hrs
Actual start: 01/26/2007
Actual finish: 03/01/2007
Actual work/cost: 46 hrs
% Complete = 100
Physical % Complete = 100
If I set Project status date to 01/25/2007, BCWP for this task is 162
and BCWS=ACWP=0.
Setting status date to 03/14/2007, the values are OK: BCWP = 162, BCWS
= 162, ACWP=46.
Is this a known bug?
Thanks,
Vitor.