I believe a variation on Julie's response will meet your needs.
Create resources called Installation Team #1, Installation Team #2, etc.
Max units for each team would be 700% as Julie said. The cost for using this
resource becomes the sum of the costs for each individual that makes up that
one team. The work for each team becomes 7*8=56 Hours/day so you have to
remember to assign it that way.... This means you only assign Team#1 at 700%
units and never anything else--- the team lives together.
So, each team can be assigned to separate jobs and move together as a group
although they were not created that way. If you owned a Pool Plastering
Company you could have Demo Team, Plaster Team, Finish Team. They would
travel to pool sites independently.
Voice of experience - Be careful. If "Johnny" is a resource, and, he is also
a member of "Installation Team #3" there is no way for Project to know if
Johnny is overallocated. You have to monitor this situation manually using
the Resource Usage and Task Usage Views.
Personally, we use Julie's method #2.
--
If this post was helpful, please consider rating it.
Jim
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project