I
Ian
I know I should know this, but...
I am scheduling backwards from a known end date. Task B is 1 day in
duration, starting at 8:00 AM on Monday and ending at 5:00 PM on Monday.
I need task A to start at 8:00 AM on Friday and end at 5:00 PM on Friday.
When I do a SF dependence of A on B, Project has A start at 8:00 AM on Friday
and end at 8:00 AM on Monday (of course, exactly matching the start date of
B).
I have tried 1 minute lags and leads with no success. Can someone give me
the obvious answer, please?
Thanks very much.
///Ian
I am scheduling backwards from a known end date. Task B is 1 day in
duration, starting at 8:00 AM on Monday and ending at 5:00 PM on Monday.
I need task A to start at 8:00 AM on Friday and end at 5:00 PM on Friday.
When I do a SF dependence of A on B, Project has A start at 8:00 AM on Friday
and end at 8:00 AM on Monday (of course, exactly matching the start date of
B).
I have tried 1 minute lags and leads with no success. Can someone give me
the obvious answer, please?
Thanks very much.
///Ian