JaneH
Hi
I have a resource that is assigned to a task when I know she is on holiday.
If I assign the resource using the resource column in the entry table, or the
assign resources button or the combination view it will (as I assumed it
would) reschedule the task to be started when she comes back from holiday.
However if I assign the resource using the task information box Project
reduces the duration of the task to zero days. I have checked this on
Project 2000 and 2003 and it happens on both versions.
I realise there may be a logical explanation for this , so my question is
why does this happen?
Should I not use the task infromation box for assigning resources?
Thanks
I have a resource that is assigned to a task when I know she is on holiday.
If I assign the resource using the resource column in the entry table, or the
assign resources button or the combination view it will (as I assumed it
would) reschedule the task to be started when she comes back from holiday.
However if I assign the resource using the task information box Project
reduces the duration of the task to zero days. I have checked this on
Project 2000 and 2003 and it happens on both versions.
I realise there may be a logical explanation for this , so my question is
why does this happen?
Should I not use the task infromation box for assigning resources?
Thanks