colembo
I am working on a tight shutdown schedule where tasks are being scheduled to
the hour. I created a 24 hour project calendar since work is generally
around the clock but can't find a way to create a new task which may start at
8AM because constraint dates don't show to the hour even though I am entering
by the hour. The only way I found to get an 8 AM start was to put 8 hours of
slack in as a task in front of the true task. Similarly when I look at task
details it simply says the date of completion and I am looking for the date
and hour?
Any suggestions? I am running Project 2000 and would be glad to upgrade if
hourly scheduling has improved.
the hour. I created a 24 hour project calendar since work is generally
around the clock but can't find a way to create a new task which may start at
8AM because constraint dates don't show to the hour even though I am entering
by the hour. The only way I found to get an 8 AM start was to put 8 hours of
slack in as a task in front of the true task. Similarly when I look at task
details it simply says the date of completion and I am looking for the date
and hour?
Any suggestions? I am running Project 2000 and would be glad to upgrade if
hourly scheduling has improved.