C
Chris Reed, P.M.U.K.
I have hit a problem with MS Project 2003 (SP2). Despite updating the Options
- Calendar dialog with 7.5 hours per day and 37.5 hours per week, the
resource usage worksheet still works to 8hrs per day.
Is there another setting I have missed?
Huge thanks for any assistance folks,
Chris