G
Guest
Hi all,
I'm trying to work this out in project. Our jobs are a fixed number of
hours and not a fixed
duration. We also each have about 5 - 10 jobs on
the go at one time so everyone's time is divided up a lot throughout the
weeks. What is the best way to do this in project? Is it to use Fixed
Work, Effort Driven setting? Is it to fill in the resource plan with
the squares in it with how many hours we work on it each week? I've
been having a lot of trouble, for example, getting the program right
when I input that someone's task is to spend 3 hours per week with a
certain client until the end of the year. It isn't really fixed work,
it's just ongoing consulting every week.
Any help that anyone can give me would be greatly appreciated.
Thanks and regards,
Angus Duncan
I'm trying to work this out in project. Our jobs are a fixed number of
hours and not a fixed
duration. We also each have about 5 - 10 jobs on
the go at one time so everyone's time is divided up a lot throughout the
weeks. What is the best way to do this in project? Is it to use Fixed
Work, Effort Driven setting? Is it to fill in the resource plan with
the squares in it with how many hours we work on it each week? I've
been having a lot of trouble, for example, getting the program right
when I input that someone's task is to spend 3 hours per week with a
certain client until the end of the year. It isn't really fixed work,
it's just ongoing consulting every week.
Any help that anyone can give me would be greatly appreciated.
Thanks and regards,
Angus Duncan