how can I add a status coloum with percentage indicate

J

Jenny Li

Hello,

I run into a problem when I insert a coloum of status, instead of getting
the % indication, I got the complete or 'future task', what should I do to
turn it into % indicate, thank you
 
J

JulieS

Hello Jenny Li,

Try inserting either the % Complete column or the % Work Complete column
instead of the Status column.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top