Thanks Steve
Alt F5 works in that it takes me to the red values next to the resources in
question.
However that does not really tell me what I need to find out...Sorry I think
I am missing something here...
all MS Project is telling me is that resource AP is working for 2.2 hrs on
friday 10th November and is highlighting 2.2 hrs in red. Now bearing in mind
that this resource has 100% allocation and a default calendar of 40 hrs per
week I need to show when tasks are clashing, as 2.2 hrs in a day is not
enough to be overallocated. I understand MS Project will highlight
overallocation even if 8 hours of work have not been reached as long as the
tasks time clash. Where can I see the 'time stamp' for the tasks?
Many thanks again
Ilaria
:
Sorry about that - had a Senior Moment. Should have said [Alt][F5]. My
bad.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Hi Steve
thanks for your reply, however it does not work for me. Ctrl F5 jsut make
my
window smaller. Any other suggestions?
Many thanks
:
In the resource usage view, press [Ctrl][F5] and it will jump you from
overallocation to overallocation.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Please could you tell me how to identify the tasks that cause
overallocation?
I understand the principle behind overallocation, however cannot find a
way
to see what task is clashing on which day. I dont want to trail through
all
of the tasks...Many thanks