How can I insert a new task in project if the option is grayed ?

  • Thread starter Tommy-Project 2007 Novice
  • Start date
T

Tommy-Project 2007 Novice

I am trying to insert a new task into the middle of an existing chart, but
the option to insert a new task is grayed out. It will let me add one to the
bottom of the chart works, but how can Insert lines in the middle?
 
M

Mike Glen

Hi Tommy,

Welcome to this Microsoft Project newsgroup :)

From the Gantt Chart view, click where you want the task to go. Then select
Insert/New Task or click the Insert button on your keyboard. Does that
work? You could also try right-clicking the ID number of the task below
where you want it to go and select New Task.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials



"Tommy-Project 2007 Novice" <Tommy-Project 2007
(e-mail address removed)> wrote in message
news:[email protected]...
 
J

Jim Spiller

You can't Insert if the chart is Grouped. Remove Grouping by selecting
Project-Group by-No Group.


"Tommy-Project 2007 Novice" <Tommy-Project 2007
(e-mail address removed)> wrote in message
news:[email protected]...
 