How can I put a task in Project without a date?

M

Mark B

That functionality is not available in Project.

Regards

Mark Brownlee
Orbisoft Customer Care
(e-mail address removed)

New! Orbisoft Releases Task Manager 2005T Task / Project Management Software
=================================================================
Vist www.orbisoft.com to download a FREE trial of Task Manager 2005T
 
S

Steve House [MVP]

Are you wanting to do this because the dates are still to be determined? In
a very real sense you should be entering all of the tasks without dates
anyway. That's not to say the task will have blank dates in the plan once
you enter it. Since a task is a physical activity performed by a resource
that extends over a finite and observable period of time, it simply can't
exist in the plan without the dates where the activity is expected to take
place. As the plan evolves the dates may change but that's not the same
thing as not having dates at all. That's why you use scheduling software
such as Project in the first place. When you input the task information -
name, duration estimate, relationship to other tasks, resources required -
it calculates the dates for you where you should be scheduling it and
displays those in the plan. If conditions change later, the expected
schedule dates will also change but for it to be a plan at all, the element
of time as well as the nature of the task must be present. How else will
you advise the resources when they need to engage in the scheduled activity?
 
J

Joe

Perhaps all you really need is a simple excel spreadsheet. Sounds like all
you really need/want is a to-do list.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top