A
Ann
I have a resource with an assignment unit of 15% and task duration of 4 days.
The problem is that Project is not scheduling the work according to the
resource's assigment units. It shows the finish date 4 days after the start
date, even though the resource is only dedicated to the project 15%.
What am I doing wrong? I've tried task type of fixed duration
effort-driven, fixed duration not effort-driven, fixed units effort driven,
fixed units not effort driven, and fixed work...and I always end up with the
task being finished 4 working days after the start date, even though the
resource would take more like 27 working days to finish this, based on their
assignment units. I am definitely not understanding this correctly!!
The problem is that Project is not scheduling the work according to the
resource's assigment units. It shows the finish date 4 days after the start
date, even though the resource is only dedicated to the project 15%.
What am I doing wrong? I've tried task type of fixed duration
effort-driven, fixed duration not effort-driven, fixed units effort driven,
fixed units not effort driven, and fixed work...and I always end up with the
task being finished 4 working days after the start date, even though the
resource would take more like 27 working days to finish this, based on their
assignment units. I am definitely not understanding this correctly!!