How do I add a baseline to a summary task in Project 2000?

C

colin919

Added baseline to entire project, but only shows up on subtasks. How do I add
the baseline to the summary tasks as well?
 
J

JulieD

Hi

choose the view that you want to add this to (e.g. the tracking gantt view)
then go into format / bar styles and create a new bar for the summary tasks
on the first blank line in the list at the top type
NAME: SummaryBaseline(or whatever you want to call it)
APPEARANCE: set a style by choosing from the options in the bottom half of
the screen
SHOW FOR .. TASKS: choose summary
ROW: 1
FROM: Choose baseline start
TO: choose baseline finish

Click OK and it should show up now.

Cheers
JulieD
 