E
ed of tulsa
how do i add a task that automatically changes duration to match the overall
project duration? for example, an administrative assistant will be assigned
at the beginning of the project and will continue until the end of the
project - regardless of subsequent changes to the schedule. another way of
looking at this is how can i assign resources to the Project Summary Task (ID
0)?
project duration? for example, an administrative assistant will be assigned
at the beginning of the project and will continue until the end of the
project - regardless of subsequent changes to the schedule. another way of
looking at this is how can i assign resources to the Project Summary Task (ID
0)?