Hi Natalie,
There are no buttons to push to add lag.
1)Create the link between the tasks.
2)Double click on the successor task to show the Task Information dialog
box.
3) Click the Predecessor tab in the Task Information dialog box and add
the lag in the lag field.
You can also double click the link line in the Gantt chart view to show
the Task Dependency dialog box and add the lag there.
I hope this helps. Let us know how you get along.