how do i add in lag time??

N

nataliemarylang8

I actually want to know wat buttons exactly to press to add in lag time
please can someone help me
Thank you
 
J

JulieS

Hi Natalie,

There are no buttons to push to add lag.

1)Create the link between the tasks.
2)Double click on the successor task to show the Task Information dialog
box.
3) Click the Predecessor tab in the Task Information dialog box and add
the lag in the lag field.

You can also double click the link line in the Gantt chart view to show
the Task Dependency dialog box and add the lag there.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
N

nataliemarylang8

Hey thank you so much lol i knew there was not an exact button to press but
i wanted to know the extact things i need to click, if you know what i mean
all sorted now thanks
 
J

JulieS

You're welcome Natalie and thanks for the feedback. Glad you got things
sorted.

Julie
Project MVP
 