P
Patrick
Hi
I have a consolidated project plan that has a list of clients first and then
specific tasks indented underneath them. So, it's like
Client 1
- Software Installation (John) 10/10 - 10/14
Client 2
- Technical meeting (Sue, John) 10/4 - 10/6
- Software installation (John) 10/17 - 10/19
I would like to use the Who Does What When report to see where folks are in
the coming weeks, but it only shows the task name and not the task summary
name. So I can see what they are doing, but not for which client. Our tasks
are all standardized in terms of naming, so a particular person does many of
the same tasks and it's really more important to know where they are doing
it. so in the example above, I would just see
John
- Software Installation 10/10 - 10/14
- Software Installation 10/17 - 10/19
Is there a way to view the Task Summary name so it would read like this
instead?
John
- Software Installation Client 1 10/10 - 10/14
- Software Installation Client 2 10/17 - 10/19
I have seen where if you get the Usage table, it does try and show Task
Summary Name, but it doesn't explode the rows so I only see a single,
collapsed row for each resource and not the task activity.
Thanks so much!
I have a consolidated project plan that has a list of clients first and then
specific tasks indented underneath them. So, it's like
Client 1
- Software Installation (John) 10/10 - 10/14
Client 2
- Technical meeting (Sue, John) 10/4 - 10/6
- Software installation (John) 10/17 - 10/19
I would like to use the Who Does What When report to see where folks are in
the coming weeks, but it only shows the task name and not the task summary
name. So I can see what they are doing, but not for which client. Our tasks
are all standardized in terms of naming, so a particular person does many of
the same tasks and it's really more important to know where they are doing
it. so in the example above, I would just see
John
- Software Installation 10/10 - 10/14
- Software Installation 10/17 - 10/19
Is there a way to view the Task Summary name so it would read like this
instead?
John
- Software Installation Client 1 10/10 - 10/14
- Software Installation Client 2 10/17 - 10/19
I have seen where if you get the Usage table, it does try and show Task
Summary Name, but it doesn't explode the rows so I only see a single,
collapsed row for each resource and not the task activity.
Thanks so much!