How do I assign a task 2 hours per day from start to end date?

G

genoelsabio

I have a task that needs to be done for 2 hours each day from the start date
of the task to the end date. How do I assign only that time to the project?

Many of the functions of this project are small tasks done daily for a
duration. This is one solution for multiple tasks.

Thanks for any help you can provide.
 
M

Mike Glen

Hi genoelsabio ,

Welcome to this Microsoft Project newsgroup :)

Please see FAQ Item: 19. Hammock Tasks. Then assign a resource at 25%,
assuming an 8-hour hay.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top