P
Philip
I have a project where there are multiple resources, each having a calendar
showing work availability. The project itself has its own calendar and the
tasks are based on timeframes throughout the workweek. i.e. task1 is monday,
wednesday and friday from 7:00 am to 10:00 am; task2 is tuesday and thursday
from 7:30 am to 11:00 am. I need to assign 3 resources to each of the tasks
that have their own calendar showing times that they can/cannot work. I want
develop within Project (2003) to auto-assign resources to the tasks.
Any suggestions are greatly appreciated
showing work availability. The project itself has its own calendar and the
tasks are based on timeframes throughout the workweek. i.e. task1 is monday,
wednesday and friday from 7:00 am to 10:00 am; task2 is tuesday and thursday
from 7:30 am to 11:00 am. I need to assign 3 resources to each of the tasks
that have their own calendar showing times that they can/cannot work. I want
develop within Project (2003) to auto-assign resources to the tasks.
Any suggestions are greatly appreciated