L
Lonnie Bowling
Assigning Resources in Project Server 2007
I am trying to come up with a way to allow a resource manager to assign his
resources from the enterprise resource pool to a various project tasks (that
come for all the current active projects). I would like the manager to be
able to view all tasks assigned to his group (using generic resources) and be
able to adjust a task start/stop dates and assign a real resource to it. It
appears that in the resource center you can see resource assignments and
availability but there is no ability to actually change these items. Any
ideas on how to set this up would be very helpful.
Lonnie Bowling
I am trying to come up with a way to allow a resource manager to assign his
resources from the enterprise resource pool to a various project tasks (that
come for all the current active projects). I would like the manager to be
able to view all tasks assigned to his group (using generic resources) and be
able to adjust a task start/stop dates and assign a real resource to it. It
appears that in the resource center you can see resource assignments and
availability but there is no ability to actually change these items. Any
ideas on how to set this up would be very helpful.
Lonnie Bowling