C
Catheleen
We are using EPM 2007 with global resources and Project Templates. We have
recently noticed that if we do the following steps a specific resource
disappears from our Project.
1. Open New EMP Project Template
2. Save and publish
3. Start assigning Resources using Build Team from Enterprise
Once we change General Project Manager to a specific Project Manager this
then deletes other resources completely from the plan UPON SAVING.
We now use the following workaround but would like to resolve the issue.
1. Open New EMP Project Template
2. Start assigning Resources using Build Team from Enterprise
3. Then save and publish.
The issue is repeatable.
recently noticed that if we do the following steps a specific resource
disappears from our Project.
1. Open New EMP Project Template
2. Save and publish
3. Start assigning Resources using Build Team from Enterprise
Once we change General Project Manager to a specific Project Manager this
then deletes other resources completely from the plan UPON SAVING.
We now use the following workaround but would like to resolve the issue.
1. Open New EMP Project Template
2. Start assigning Resources using Build Team from Enterprise
3. Then save and publish.
The issue is repeatable.