How do i get a total of the duration for all Tasks?

M

Mr Moore

Hi All,
Im pretty new to project and i have listed all my tasks and durations and
mapped them out in the gannt chart. All i want now is a total of the
durations i have entered. It seems like a simple thing to me. Anyone know how
this is done?

Cheers
 
J

John

Mr Moore said:
Hi All,
Im pretty new to project and i have listed all my tasks and durations and
mapped them out in the gannt chart. All i want now is a total of the
durations i have entered. It seems like a simple thing to me. Anyone know how
this is done?

Cheers

Mr Moore,
Go to Tools/Options/View tab. In the lower right corner you will find an
option for the Project Summary Task. Check it and hit "ok". You will now
have a top level Summary line with a Duration for the whole project.
Keep in mind however that the Duration of a Summary line is not the
arithmetic sum of all task Durations in the Project, rather, the
Duration of a Summary Line is the working time between the Start date of
the earliest task in the project and the Finish time of the latest task
in the project.

Hope this helps.
John
Project MVP
 
M

Mr Moore

Cheers for that John,

I have already tried that from looking at previous forum posts. What i
actually need is a total of all durations. As some run concurrently with each
other it really doesnt give me a true account of how much time the whole
project will take in terms of hours worked. I need these totals so i can
quote clients. Any idea how i get a total sum of all duration times?

Cheers
 
B

Brian K - Project MVP

Mr said:
Cheers for that John,

I have already tried that from looking at previous forum posts. What
i actually need is a total of all durations. As some run concurrently
with each other it really doesnt give me a true account of how much
time the whole project will take in terms of hours worked. I need
these totals so i can quote clients. Any idea how i get a total sum
of all duration times?

Cheers

I think you want the sum of Work for such a quote to a client. The sum
of durations over the course of a 1 month project could be several
years and would not be directly indicative of the number of hours
worked on the project. Insert the Work field after inserting the
Project Summary task and you will get the sum of all the Work (effort)
on the project.

Does that help?
 
M

Mr Moore

Ah thanks Brian.

It seems i am putting the time worked in the wrong column if i put it in the
work column it does total in the summary.

Cheers for the help.
 
B

Brian K - Project MVP

Mr said:
Ah thanks Brian.

It seems i am putting the time worked in the wrong column if i put it
in the work column it does total in the summary.

Cheers for the help.

I wish I had a dime for every person that ever got Duration and Work
mixed up! :)

No problem! have a good evening\day\night.
 
S

Steve House [Project MVP]

Be very very careful - Work and Duration are two totally different (though
related) measures even though they're both listed in hours and you need to
make sure you always compare apples to apples and oranges to kangaroos <g>.
Work measures the amount of effort required to produce the project's
outcome, it's what you pay people to do and your client or customer pays you
to achieve for him. Work hours are a measure of sweat. Duration is the
length of time over which the work is accomplished. It extends from the
instant work first is done and until the instant work is finished but
completely ignores whether the work is continuous or how many people are
working during that time period. Duration hours measure the passage of time
during which work could have been done, without regard to how much of it
actually was done or not. If Joe spends an hour painting a wall on Monday
morning, then lets it dry until late Tuesday afternoon when he comes back to
spend an hour finishing all the trim, the duration of the painting task will
be 16 hours but the work would be 2 hours. OTOH, if you have 3 guys working
together on something all day Monday, the duration will be 8 hours but the
work will be 24.

You know your project and obviously I don't but I will say this - although
the total length of the project, the distance between the start date and the
end date, is certainly important, in 99.99% of projects, the arithmetic sum
of the task durations is a completely meaningless number and corresponds to
the project's overall duration only by rare accident. On the other hand,
the sum of work - the hours you're paying for - is very very important.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top