J
jbossert
I need to reserve 40% of my time for the task "Project Management",
preferably . I'm using a standard calendar for the project and myself.
If I assign the resource "Me[40%]" to the task, Project spreads the task,
but doesn't assign any other tasks to me until <after> the "Project
Management" task is finished. Effectively, it's created a new calendar for
me that only allows 40% of my time to be allocated ** to the total project **
I want to be able to spend 3.2 hours each day on PM, with the remaining 4.8
(standard calendar) allocated to any other tasks in the project.
preferably . I'm using a standard calendar for the project and myself.
If I assign the resource "Me[40%]" to the task, Project spreads the task,
but doesn't assign any other tasks to me until <after> the "Project
Management" task is finished. Effectively, it's created a new calendar for
me that only allows 40% of my time to be allocated ** to the total project **
I want to be able to spend 3.2 hours each day on PM, with the remaining 4.8
(standard calendar) allocated to any other tasks in the project.