S
SAIFUL
I NEED TO SET UP MY MACHINERY AND TO SCHEDULE THE MATERIAL BASED ON MY
MACHINERY OUTPUT(MATERIAL) PER DAYS AND I NEED TO PRODUCE THE HOW MANY
(QUANTITY) SHOULD BE DONE BY THIS MACHINERY/MONTH.
EXAMPLE:
EXCAVATOR 1
OUTPUT: 300m3/DAYS
THIS MACHINERY I NEED TO PUT AS RESOURCES WITH TYPE OF 'MATERIAL' NOT
'WORKS' SO THE OUT PUT IN SCHEDULE WILL IN MATERIAL OR m3 NOT HOURS.
THE QUANTITY TO CLEAR=30,000m3
SO HOW MANY QUANTITY FOR MONTHLY SCHEDULE OUTPUT /MONTH FOR THIS MACHINERY.
I NEED THE SCHEDULE BASED ON THE MATERIAL NOT HOUR OR TIMES OF USAGE.
AND HOW TO INSERT THIS RATE OF USAGE (IN MATERIAL NOT MONEY)
MACHINERY OUTPUT(MATERIAL) PER DAYS AND I NEED TO PRODUCE THE HOW MANY
(QUANTITY) SHOULD BE DONE BY THIS MACHINERY/MONTH.
EXAMPLE:
EXCAVATOR 1
OUTPUT: 300m3/DAYS
THIS MACHINERY I NEED TO PUT AS RESOURCES WITH TYPE OF 'MATERIAL' NOT
'WORKS' SO THE OUT PUT IN SCHEDULE WILL IN MATERIAL OR m3 NOT HOURS.
THE QUANTITY TO CLEAR=30,000m3
SO HOW MANY QUANTITY FOR MONTHLY SCHEDULE OUTPUT /MONTH FOR THIS MACHINERY.
I NEED THE SCHEDULE BASED ON THE MATERIAL NOT HOUR OR TIMES OF USAGE.
AND HOW TO INSERT THIS RATE OF USAGE (IN MATERIAL NOT MONEY)