how do i not display zeroes in project

D

Doug Wilson

I would like to only display days when a resource actually works in Project
2003....right now it displays 0h on days that the employee isnt working and a
lag has been inserted. Any suggesations?
 
J

John

Doug Wilson said:
I would like to only display days when a resource actually works in Project
2003....right now it displays 0h on days that the employee isnt working and a
lag has been inserted. Any suggesations?

Doug,
Sorry, Project doesn't have the flexibility to suppress zeros. For that
you will need to export the data to another app.

John
Project MVP
 