R
Rich Asher
Hi,
brand new to using Project so need some help for my course! have had to draw
an activity on arrow network, fully analysed and compare it with gantt chart
on the PC; my project is due to end later than it technically needs to so to
compare float etc I need to put an end date in but not schedule tasks from
that date - schedule from start date.This should then spread the tasks
accordingly with plenty of float?
Many thanks
brand new to using Project so need some help for my course! have had to draw
an activity on arrow network, fully analysed and compare it with gantt chart
on the PC; my project is due to end later than it technically needs to so to
compare float etc I need to put an end date in but not schedule tasks from
that date - schedule from start date.This should then spread the tasks
accordingly with plenty of float?
Many thanks